    G'day. I'm Aidan from KDEC and we've just pulled up at one of our recent SunPower Reserve installations and we're going to get in there and I'm going to show you how to do the startup and shut down procedures of your system.
  • 0:14
    So let's go take a look.
  • 0:17
    Here we are at our switchboard. This is our changeover switch here.
  • 0:20
    We just need to switch him down to mains to bypass our inverter.
  • 0:24
    Let's head back to the reserve. All right, here we are at our SunPower reserve system.
  • 0:29
    Now any KDEC installed system, you'll find a startup shutdown procedure somewhere next to your system.
  • 0:34
    Now when you're following these, do be careful.
  • 0:36
    They're slightly different order of steps, depending if you're shutting down or starting up, and your system's nearly always going to be on when you're going through this.
  • 0:43
    So we'll go ahead and follow the shutdown procedure here.
  • 0:46
    First step, set the changeover switch to mains to supply loads from the grid.
  • 0:50
    Now this is in your switchboard, so let's jump over to your switchboard and have a look.
  • 0:56
    Alright, back with the reserve, steps two and three, switch off the main switch UPS EPS supply and switch off the main switch battery inverter supply.
  • 1:05
    That's your two isolators here. So we'll go ahead and switch them off in their order, EPS and the mains.
  • 1:12
    All right, now for steps four and five, we need to remove this cover on the inverter here.
  • 1:17
    So your isolators and brokers are under here, so we'll just lift up and push back.
  • 1:22
    Now under here we need to get to our PV array DC isolator that's tucked in the back here.
  • 1:27
    It'll be clearly labelled and the off and on positions on it are also labelled.
  • 1:30
    So we'll go ahead and switch that off, and then we'll come through to our battery system DC isolator, and we'll switch that off also.
  • 1:37
    For our next step, we need to get to the isolators on the battery itself. They're located on this panel on the right.
  • 1:42
    So to get this panel off, we just push back, lift out, it'll come away.
  • 1:47
    Now you can see we've got another breaker here, so we'll just flick that off.
  • 1:52
    And our final step, we need to hold this button down for six seconds, so we'll count that out. One, two, three, four, five, six.
  • 2:03
    Now you should see all your lights on your inverter are completely off.
  • 2:08
    Now we can go ahead and go through our start up procedure, can get us back online.
  • 2:13
    All right, so now that our shutdown procedure is complete, we can go ahead and follow our startup procedure and get ourselves running again.
  • 2:20
    So first step, we'll flick on that battery breaker. So this is just the breaker and we flick that on.
  • 2:27
    Next we come over this side for our battery system breaker and we flick this up.
  • 2:33
    Should be in the up position to turn it back on, back across to the side of our battery again, we need to get to that button, and this time we're just holding down for one second.
  • 2:41
    You should see the lights on the battery come on.
  • 2:43
    Very good. We can move to our inverter.
  • 2:46
    So next we flick on our AC, first the battery inverter AC isolator, and then our EPS AC isolator.
  • 2:54
    Now we jump back in here and we get to that PV array DC isolator.
  • 2:58
    We need to flick that back down to the on position, and we're all set to get round to our switchboard for our final step, and just put that changeover switch back to auxiliary.
  • 3:09
    Alright, so back around at our switchboard and our final step to get ourselves back up and running properly.
  • 3:13
    We just flick our changeover switch back up to auxiliary and that's all done.

In this video, the KDEC team will demonstrate how to correctly shut down and restart your Sunpower Reserve system. Following the correct sequences when powering off or restarting the Sunpower Reserve is vital to prevent damaging its sensitive components and avoid disrupting the battery management system. To learn how to properly shut down and restart your Sunpower Reserve, watch this quick and easy-to-follow instructional video. Through this guide, you’ll be able to maximise your system’s performance and protect its integrity.

If you want to learn more about the Sunpower Reserve or if you have any questions about this solar battery solution, you may get in touch with a specialist from KDEC by calling us at 02 6021 6033 or sending us an email at kdec@kdec.com.au.

Committed to delivering clean energy solutions

As Albury Wodonga's leading solar experts, Kdec’s promise of quality service is guaranteed with our roster of trained and licensed Electricians. Whether you’re a commercial business, a new homeowner or looking to upgrade your family home, our 25 years of experience means you’re in safe hands.

Talk to a KDEC team member

Our Office

30 Ruby Court, Albury 2640

Contact Us

  • 02 6021 6033
  • kdec@kdec.com.au
facebook instagram

Quick Links

  • About KDEC
  • KDEC Team
  • Clients & Suppliers
  • Blog
  • KTECH
  • Contact Us
  • FAQ

Our Solutions

  • Solar Solutions
  • Solar Consultancy
  • Electrical Solutions
  • Fibre and Data Solutions
  • EV Chargers

Our Works

  • Industrial
  • Commercial
  • Domestic
  • Fibre and Data
  • Case Studies

Licence Number: NSW 363462C | Vic 29085
© Copyright 2021 by KDEC Electrical. All rights reserved.
Website by Digital Marketer Bee.

4.9
Based on 109 reviews
powered by Google
js_loader